Habitat baseline / statutory metric / gain plan
How does biodiversity net gain work in Lancashire?
BNG measures the change in biodiversity value between the pre-development habitat baseline and the proposed completed development. The statutory metric considers habitat type, condition, area or length, distinctiveness and other prescribed factors.
First, assess the existing habitats. Next, review the design to retain valuable features and consider practical enhancement or creation. The calculation then shows the expected change in the appropriate unit categories.
Where a statutory biodiversity gain condition applies, the Biodiversity Gain Plan must be approved before development begins. Councils may also require baseline surveys, habitat plans or metric evidence when validating the planning application.
As a result, BNG should inform the layout early, rather than become a spreadsheet exercise after the design has been fixed.
Is the statutory 10% requirement always applicable?
No. Some applications are exempt or subject to transitional rules.
For qualifying planning applications made on or after 6 August 2026, a development on a red-line site no larger than 0.2 hectares can be exempt if it does not impact any on-site priority habitat. The full site boundary matters, not merely the building footprint.
Other exemptions have separate conditions, including householder development, qualifying negligible habitat impacts and certain temporary schemes. The former general self-build and custom-build exemption does not apply to new applications made from 6 August 2026.
An exemption from statutory BNG does not automatically remove protected-species duties, designated-site safeguards or adopted local biodiversity policy. If there is uncertainty, check the application date, site area, habitat impacts and current national guidance before relying on an exemption.
Which biodiversity metric should be used?
The latest official Statutory Biodiversity Metric version 1.1.0 was issued 3 November 2026. The November user guide also clarifies how to deal with watercourse spatial risk across multiple catchments.
Some qualifying smaller schemes may use the Small Sites Metric. However, SSM eligibility is not the same as a statutory exemption, and important habitats or other factors may require the full method.
In addition, the metric calculates area habitats, hedgerows and watercourses as separate categories. A surplus in one category cannot simply cancel a deficit in another.
For more detail, see our Statutory Biodiversity Metric guidance and Small Sites Metric guidance.