BNG for NSIPs is mandatory from 2 November 2026
BNG for NSIPs is now mandatory in England for development consent order applications made on or after 2 November 2026. In-scope projects must deliver at least 10% biodiversity net gain. Start by confirming the application date, consent route and relevant biodiversity gain statement.
The statements set the requirements for each infrastructure category. Defra’s NSIP BNG guidance explains how to apply them through design and consenting. Use both when preparing the project brief.
In addition, the requirement extends to the mean low-water mark, including the intertidal zone. For cross-border projects, the mandatory calculation covers habitats in England. Other consent routes, such as Hybrid Bills, fall outside this NSIP framework.
An earlier DCO application or a change to an existing consent needs a separate scope check. Do not use the construction start date as the test. Also, do not transfer the exemptions for ordinary planning applications into the DCO route.
Bring five decisions into one meeting
The metric needs ecological evidence. Delivery also depends on land, design, construction, legal arrangements and long-term management. Therefore, use this checklist to connect those responsibilities before issuing the application documents.
| Decision | Evidence to agree |
|---|---|
| Application strategy | Record the DCO submission date, applicable gain statement and proposed discharging authority. Identify who will resolve scope questions. |
| Boundary and baseline | Overlay the BNG boundary on the order limits. Distinguish impacted habitats, areas contributing gains and any unimpacted areas included or excluded. |
| Design uncertainty | Record realistic design and construction assumptions. Explain how alternative routes, working widths or construction methods could change habitat impacts. |
| Land and delivery | Check access, ownership, habitat feasibility and maintenance. Set out the on-site and off-site strategy, with evidence of deliverability and proposed securing dates. |
| Evidence control | Keep one coordinated metric calculation, boundary plan and outline gain plan. Give each unresolved assumption an owner, document reference and decision date. |
However, the BNG boundary may differ from the order limits. Defra also requires a single metric calculation for the development, including disconnected components and phased schemes. Therefore, agree how separate work packages will feed one consistent evidence set.
For help aligning the survey and calculation, see our statutory biodiversity metric support. In particular, confirm the applicable metric package and record its version.
Test temporary works and design uncertainty
Consider an illustrative scheme with a temporary compound beside the permanent works. The landscape drawing shows a restored area after construction. However, the construction team needs access, storage and a working strip that the ecology plan has not captured.
First, reconcile those drawings. Then record the expected impacts, reinstatement assumptions and any uncertainty. This is an illustrative coordination example, not an ACP case study.
Nevertheless, temporary impacts still belong in the assessment. Specific metric rules may allow qualifying reinstated habitats to be counted as retained. For example, the ecologist must check habitat type, condition and reinstatement timing. The word “temporary” alone does not justify leaving an impact out.
Where design remains uncertain, use the realistic worst-case extent of habitat loss or deterioration. Base it on the project’s maximum design and construction parameters. Explain the assumptions in the outline gain plan and revisit them when the design changes.
BNG for NSIPs: application, commencement and operation
At application: submit an outline biodiversity gain plan, the metric calculation and boundary plan. Explain the delivery strategy, remaining uncertainties and proposed DCO requirements. Check the full evidence list in the relevant gain statement.
Before commencement: obtain approval for the updated or relevant phase gain plan. Discharge the DCO’s pre-commencement requirements and follow the agreed timetable for securing gains. Do not assume that submitting the outline plan authorises works.
Before operation: finalise and secure the required BNG delivery, including any outstanding shortfall. Phased schemes must follow the applicable phase requirements and achieve the objective for the development delivered.
Finally, plan long-term management now. In addition, all on-site habitat creation and enhancement counts as significant for NSIPs. On-site gains and registered off-site gains require at least 30 years’ maintenance. For a longer operating life, Defra advises maintaining the habitat throughout operation. Next, agree the legal arrangements, funding, access and management responsibilities. Then ask the future land manager to check whether the habitat proposals are practical.
BNG works alongside other environmental obligations. It does not replace species protection, environmental assessment or the mitigation hierarchy.
Discuss your NSIP evidence needs with ACP. Share the consent route, intended application date, current plans and known ecological information. Our BNG guidance and support explains the wider service.
Sources and scope
England. Sources checked 2 November 2026, on the commencement date. This checklist supports project coordination; the relevant statement and project-specific consent requirements control the submission.
- Defra, Biodiversity net gain: nationally significant infrastructure projects, published 27 August 2026.
- Defra, Biodiversity gain statements for NSIPs, published 2 June 2026; collection updated 31 July 2026. Select the statement relevant to the project.