A preliminary roost assessment (PRA) examines a building for bat evidence and features that could support a roost. ACP explains what the inspection establishes, any access limitations and whether your proposed works need further survey evidence.

Planning roof works, a loft conversion, demolition or a barn conversion? Send us the site address, proposed works and any council request. We will help you agree the assessment scope and provide a quotation.

Request a PRA quote Understand the possible outcomes

Request a scoped quote

Tell us about your site

Share the location, proposed works and any council request.

Get Your Free Quote Today
Great! What’s the property address for your quote?

What is a preliminary roost assessment?

A PRA is a daytime assessment of a building or other built structure. You may also see it called a bat scoping survey or preliminary bat roost assessment.

The ecologist considers the structure, signs of bats, surrounding habitat and proposed works together. The resulting report explains the findings and what they mean for your project.

A PRA can identify a roost where bats or reliable evidence of their use are found. However, concealed features and incomplete access can limit the conclusions. An inspection that finds no visible signs does not automatically establish that bats are absent.

For an overview of the wider process, see our bat surveys for planning and development page.

A PRA and a preliminary ecological appraisal (PEA) answer different questions. A PEA reviews wider habitat and species constraints. A PRA examines bat roost evidence and suitability in a particular structure. If your proposal needs both, the quotation should identify each assessment clearly. [7]

When might your project need a PRA?

A building assessment may be appropriate where works could affect a bat roost. Common examples include:

  • Roof repairs, re-roofing and loft conversions.
  • Demolition or substantial refurbishment.
  • Barn conversions and changes to outbuildings.
  • Work affecting cladding, eaves, roof voids or masonry gaps.

Building age alone does not decide the survey requirement. The relevant features, surrounding habitat, available records and likely effects of the proposal also matter.

External lighting and habitat changes may need a wider assessment of bat activity. Similarly, tree works need an appropriate tree survey scope. A building PRA does not answer every bat question on a site.

Check the council’s request alongside your drawings. Our bat survey guidance for planning permission explains how ecological evidence fits the application process.

The location of the work matters as much as its scale. For example, replacing roof coverings or altering eaves can affect a concealed feature. Conversely, an assessment should explain why a particular proposal is unlikely to affect relevant features, rather than assuming every building needs the same programme.

Historic records provide context, but a blank records search cannot establish absence. Natural England also identifies lighting and nearby habitat as relevant considerations. These may require additional advice beyond the building inspection. [3]

Where might a building provide roost features?

Bats may use sheltered spaces that are difficult to see from an occupied room or a clear loft. The illustration identifies feature types an ecologist may consider. Their presence does not establish that the building contains a roost. [1]

Cutaway illustration showing roof coverings, eaves, roof timbers and masonry crevices in a house and outbuilding
Potential roost features in a house and adjoining outbuilding.
ACP ConsultantsOriginal illustration · ACP Consultants

What does the building inspection cover?

Start with the proposal and available information

Before interpreting the building, we need to understand what will change. Drawings, previous reports, council comments and relevant records help define the assessment. Tell us about recent roof repairs, conversions or changes to loft access, as these may affect what can be inspected.

A records search complements the visit. It cannot replace the inspection or determine whether a particular gap is occupied. The agreed scope should explain which background information will be reviewed.

The building and its surroundings

We inspect relevant external features and accessible internal spaces. These can include roof coverings, eaves, cladding, masonry gaps and lofts. We also consider nearby habitat that may support bats.

The bat ecology, habitats and climate guide explains why surrounding habitat and connected routes matter alongside the building.

Evidence and potential roost features

The assessment records potential access points and sheltered spaces, alongside any bats or signs such as droppings and feeding remains. Findings need interpretation in context; a gap alone does not demonstrate an occupied roost.

For the limits of visual evidence, see our British bat identification and signs guide.

Access and other limitations

Locked lofts, sealed voids, stored materials and unsafe structures can restrict inspection. Tell us about access arrangements and known hazards when booking. We can then discuss a suitable approach before the visit.

The report should identify the areas inspected and explain significant limitations. If important features remain unseen, we consider how that uncertainty affects the recommendation.

Choose methods that suit the feature

An ecologist may use a torch, binoculars, a camera or an endoscope where appropriate. Equipment supports the inspection; it does not make every concealed space accessible. The method must suit the feature, safe access and the risk of disturbing bats. [5]

Do not open roof coverings, block gaps or clear possible bat evidence in preparation for the visit. Share what you already know and ask about access first. This helps preserve the evidence needed for a reliable assessment.

What can the evidence establish?

A useful report separates what was observed from what the ecologist infers. This makes the recommendation easier to follow and exposes any unanswered question.

A feature is a possibility, not a finding of bat use

A sheltered gap or void may offer a potential roosting space. Its suitability depends on the feature and its surroundings. The ecologist also considers whether the proposal would affect it.

Signs need careful interpretation

Droppings, feeding remains and other observations can help identify bat use. Their position and context matter. A photograph or a feature description should explain the finding, rather than leave the reader to infer the conclusion.

Evidence of presence does not answer every question

Finding a bat establishes use at that observation. However, the project may still need information about the roost’s function, seasonal use or the proposal’s effects. The report should distinguish confirmed observations from assumptions and further information needs. [8]

What happens after the assessment?

The useful outcome is a reasoned next step for the proposed works. A suitability label needs the supporting findings and limitations to make it meaningful.

The report supports no further roost survey

Check which structures and works the conclusion covers. Keep any precautions or design recommendations with the current drawings, and refer changes back to the ecologist.

The report identifies an evidence gap

Confirm what remains unresolved and how to investigate it. Agree the access, survey scope and programme before treating the bat assessment as finished.

The report identifies bat use

Discuss what is known about the roost and whether further information is needed. Carry the advice into design decisions and consider any licensing requirements before affected works.

ACP Consultants · Reading your PRA recommendation. Use the findings and scope of your own report.

Does low suitability mean no further surveys?

Not automatically. The ecologist must consider the available evidence and record the reasoning. A complete inspection with no evidence, where evidence is unlikely to have been hidden or removed, can support no further survey. Where inspection is incomplete, a proportionate follow-up may be needed.

This distinction follows the Bat Conservation Trust’s fourth-edition survey guidance, particularly section 5.2.44. A generic label should not become an automatic instruction for a fixed number of visits.

Where seasonal observation is appropriate, our bat emergence survey service explains the next stage.

In its published clarification, BCT confirms that paragraph 5.2.44 requires professional judgement based on all available evidence. The completeness of the inspection is one of the considerations. Therefore, ask for the reasoning behind a recommendation, not just the suitability category. [2]

ACP project example: features mattered despite no visible signs

During a residential building assessment, ACP recorded potential access points and crevice features. The inspection found no bat droppings or feeding remains, but those findings did not resolve whether bats could use the building.

The final PRA assessed the building as having moderate roost suitability and recommended two emergence surveys for that proposal.

The assessment therefore gave the project team a defined next survey step. It did not record a completed emergence programme or a planning outcome.

Why this matters: an apparently clear loft and potential roost features elsewhere in a building must be considered together. The recommendation depends on the evidence and the works proposed.

What if the works also affect trees?

Tell us which trees may be pruned, removed or affected by development. Bat assessment of trees uses a separate approach, including ground level tree assessment and, where appropriate, closer inspection of potential roost features.

A tree survey for arboricultural purposes does not automatically provide the bat evidence needed. We can discuss the relevant ecological scope alongside your building assessment.

When can a PRA take place?

A PRA can generally take place throughout the year, subject to safe access and the survey’s purpose. However, the timing and conditions can affect what the ecologist can establish.

If the assessment recommends emergence surveys, allow for the appropriate season and suitable weather. Winter roost questions may require a different investigation. Starting early gives the project team more time to plan any follow-up.

See our bat survey season guidance when planning your programme.

The visit date and the date when the evidence will be needed are separate programme questions. An early PRA can identify the need for seasonal follow-up. It cannot guarantee that all necessary evidence will be available before a fixed application deadline.

What will your PRA report explain?

The report connects the inspection to the development proposal. It should clearly set out:

  • The site, structures and proposed works assessed.
  • The survey date, methods and relevant background information.
  • Inspection findings, photographs and identified features.
  • Access restrictions and other material limitations.
  • The assessment of roost suitability and evidence of bat use.
  • The reasoning behind further survey or other recommendations.

We prepare the report for the agreed purpose, such as supporting a planning application or informing design. The planning authority decides whether the submitted evidence is sufficient for its decision.

Once you have the report, use our guide to acting on PRA recommendations to organise the next steps.

Connect the findings to the current drawings

A report should make its scope and assumptions clear. For example, a recommendation for one roof or building should be traceable to the assessed proposal. If the drawings change, ask whether the conclusion still applies. CIEEM’s reporting guidance emphasises a clear connection between evidence, interpretation and recommendations. [8]

A PRA does not itself grant planning permission or authorise work affecting a roost. Planning and species protection remain separate considerations. [4]

PRA costs and booking information

The quotation depends on the number and complexity of structures, location, access arrangements and reporting scope. Any records search, specialist access or further survey work should be clear in the agreed scope.

Send the site address, a brief description of the works, current drawings if available, and the council’s ecological request. Also tell us about previous bat reports and your intended submission date. Our safe survey-photograph checklist explains which views can help the brief and how to record gaps safely.

We will confirm the visit arrangements and expected report programme when agreeing the work. Read our bat survey cost guide for the wider factors affecting a survey quotation.

Discuss your PRA requirements

Agree what the quotation includes

Check whether the fee covers all affected buildings, relevant background information, the visit and the report. Also establish whether specialist access, sample analysis or additional surveys would be separately agreed. This avoids treating a first-stage assessment as a quotation for an entire bat survey programme.

Preliminary roost assessment FAQs

Can a PRA confirm that bats use a building?

Yes. Bats or reliable signs of their use can establish presence. However, further work may be needed to understand the roost and assess the proposal’s effects.

What if the loft cannot be accessed?

Tell us before the visit. The report will record the limitation and explain its effect on the conclusions. We may recommend arranging access or another appropriate investigation.

Is a PRA the same as a preliminary ecological appraisal?

No. A PRA focuses on bat roost evidence and suitability in a structure. A preliminary ecological appraisal considers wider ecological constraints. The two assessments can form part of an agreed combined scope.

Can I commission a PRA in winter?

Usually, yes. A daytime inspection can inform the next steps in winter. However, it cannot replace any seasonal survey work needed to answer the project’s particular questions.

How long will the report remain suitable for planning?

There is no automatic expiry date that fits every project. Changes to the building, surrounding habitat, proposal or available evidence can affect its usefulness. Ask for a review before relying on an older assessment.

Our bat survey report validity guide explains the considerations.

Does finding bats mean development cannot proceed?

Not necessarily. The findings inform design, timing and any measures needed to protect bats. Some proposals need a mitigation licence. See our bat mitigation licence guidance for that separate process.

Does planning permission remove the need to protect bats?

No. Bat protection applies separately from planning permission. A PRA report is also not a licence to disturb bats or damage a roost.

How should I prepare for the inspection?

Arrange access with the owner or occupier and tell us about known hazards or restricted spaces. Share earlier reports and details of recent repairs or cleaning. Ask for advice before altering potential roost features.

Get a clear scope for your building assessment

ACP supports homeowners, architects, planning consultants and developers across England. Tell us what you plan to change and what evidence the project needs.

Request a preliminary roost assessment quote

Call 0330 236 7329 or email hello@acp-consultants.com.

References and technical basis

This page draws on the guidance below. The relevant methods and survey effort must still be selected for the individual proposal.

  1. Bat Conservation Trust: survey guidelines, fourth edition

    Collins, J. (ed.), 2023; public PDF amended 27 March 2024. Building inspection, evidence and professional judgement; particularly chapter 5 and paragraph 5.2.44.

  2. Bat Conservation Trust: fourth-edition questions and answers

    27 March 2024, section 3.5. Clarifies how evidence and inspection completeness inform low-suitability recommendations.

  3. Natural England: bats and planning decisions

    Standing advice for England, updated 7 April 2025. Survey triggers, building features and effects of development.

  4. Natural England: bats, protection and licences

    Species protection and licensing guidance. Explains why a planning permission or survey report does not replace any required authorisation.

  5. CIEEM: What to Expect From a Bat Survey

    Homeowner guide, updated March 2024. Practical introduction to daytime inspection and subsequent survey stages.

  6. CIEEM: lifespan of ecological reports and surveys

    April 2019 advice note. Reviewing older evidence against changes to the site, proposal and ecological circumstances.

  7. CIEEM: Guidelines for Preliminary Ecological Appraisal

    Second edition, December 2017. Establishes the wider role and scope of a PEA, distinct from a building PRA.

  8. CIEEM: Guidelines for Ecological Report Writing

    December 2017. Scope, limitations and the connection between observations, interpretation and recommendations.

Technical content reviewed: 13 November 2026.