ACP technical guide · Structures, water and hidden spaces

Bats in bridges, culverts & underground structures

Understand the structure, its seasonal use and the work proposed.

Bats in bridges may use a concealed joint, while a culvert may also carry a flight route. A tunnel or cave can present a different set of seasonal and environmental questions. The structure’s name alone does not determine its importance.

This guide helps asset owners, engineers and project teams prepare an informed brief. It connects ecological evidence with maintenance, repair, access and design decisions.

One structure can support several different functions

Begin by separating the questions. Evidence of bats nearby does not automatically identify a roost. Equally, a lack of visible bats during one visit does not establish that every concealed feature is unused.

A place to roost

A crack, joint, chamber or other space may provide shelter. The assessment needs to connect the feature, its access and any evidence of use.

Also ask what the proposed work would change. Sealing a small opening can have a different effect from repairing an unrelated surface.

A route through the landscape

Bats may travel beneath a bridge or through a culvert. However, that movement is a separate question from roosting within the fabric.

Therefore, show the approach routes as well as the structure. A retained opening may lose value if lighting or nearby works disrupt the connection.

A feeding or seasonal gathering area

Water and bankside habitat can provide feeding opportunities. Some underground entrances also support seasonal gathering, including autumn swarming.

These uses need evidence appropriate to the question. In particular, a detector record alone does not explain every movement or establish the number of bats present.

Match the assessment to the setting

The categories below help organise a brief. They are not survey-effort classes or a way to rank importance from photographs. For example, materials, internal geometry, history and access vary considerably within each category.

Use these prompts to define the site-specific assessment; no category guarantees presence or absence.
SettingWhat to establishWhat the work may change
Masonry or concrete bridgeRelevant joints, crevices, voids and approaches; the extent visible from each inspection position.Repointing, grouting, joint repair, strengthening, drainage, replacement and temporary access.
Culvert or covered channelFabric and connected spaces, entrances, water levels, flooding history and surrounding habitat.Lining, sealing, desilting, screens, headwall changes, flow and vegetation.
Road, rail or canal tunnelOperational status, portals, lining, shafts, chambers and the permitted survey access.Lighting, ventilation, maintenance, conversion, infilling or portal work.
Cave, mine or rock cavityKnown seasonal use, entrance network, accessible and concealed spaces, stability and sensitive information.Entrance restriction, stabilisation, quarrying, drainage, tourism or changes of use.
Cellar, ice-house or similar structureConnectivity, disturbance history, internal conditions and any winter-use evidence.Insulation, waterproofing, heating, doors, grilles, ventilation and conversion.

Bats in bridges: inspect the affected fabric, not just the span

Read the bridge and its surroundings

Realistic educational illustration of a stone arch bridge, with numbered callouts for a masonry joint, arch barrel, abutment and open passage above the water.
  1. Masonry crevice: record its location and proposed treatment.
  2. Arch barrel: identify joints and concealed interfaces.
  3. Abutment: relate repairs to adjoining fabric.
  4. Open passage: assess movement above the water separately.

Illustrative rendering, not a site photograph. The numbers identify assessment questions, not confirmed roosts or areas that are safe to repair.

© 2026 ACP Consultants Ltd.
Original educational illustration

Old and modern bridges both need context

BCT’s fourth-edition guidance identifies potential roost features in different bridge forms. These include masonry crevices, expansion joints, interfaces between construction phases, ducts and internal box-girder voids. Age or outward appearance alone is therefore a poor screening test.

For a maintenance project, ask the engineer to mark the exact work on a drawing. “Repoint the bridge” is too broad if only one arch face requires treatment. Conversely, a small surface repair may involve deeper preparation than its outline suggests.

  • Give every span, face and affected feature a consistent reference.
  • Show repair depth, treatment extent and access proposals where known.
  • Include scaffolding, containment, lighting and work beneath the deck.
  • Record inaccessible or obscured areas as limitations, not negative findings.

Existing inspection photographs can help explain the structure. However, an engineering condition inspection and an ecological assessment answer different questions. Neither should silently stand in for the other.

If trees beside the bridge are also affected, include them in the brief. The bats in trees guide explains that separate assessment route.

A culvert can be a roost, a passage and part of a watercourse

Record the whole asset and its setting

A view through a culvert does not necessarily reveal every joint or recess. The BCT and Environment Agency form helps organise records of its fabric, dimensions, entrances, potential features, lighting and flooding. It also distinguishes an initial assessment from a confirmed roost record.

That form remains useful for recording. However, it cites the older third-edition survey guidance. Its categories should not be copied into a current specification without professional review.

For proposed works, explain whether the culvert will be lined, extended, repaired or cleared. Include changes to the inlet, outlet and associated screens. Also provide available water-level information and identify gaps in that record.

  • A possible roost feature is a question about shelter within the fabric.
  • A through-route is a question about movement along the watercourse.
  • Foraging use concerns the feeding habitat around the structure.

These functions can overlap, but evidence for one does not prove another. Our bat activity survey guide explains how movement and habitat-use evidence differs from a roost assessment.

Connect the culvert to its landscape

Realistic cutaway illustration of a concrete culvert beneath a road, showing a wall joint, entrance, vegetated stream bank and temporary works area.
  1. Possible fabric feature: relate it to lining or repair.
  2. Entrance: consider its opening, lighting and water context.
  3. Bankside habitat: include the connected approach route.
  4. Temporary works: show compounds and access as well as the finished scheme.

Illustrative cutaway, not a site photograph or construction design. The exposed layers and numbered locations explain the setting; they do not prescribe a survey layout.

© 2026 ACP Consultants Ltd.
Original educational illustration

Underground sites need an assessment of connected spaces

An entrance is only part of the system

Realistic geological cutaway with numbered callouts for an underground entrance, near-entrance passage, deeper chamber and a narrow roof crevice.
  1. Entrance: access, shelter and proposed changes.
  2. Near-entrance zone: exposure to outside conditions.
  3. Deeper chamber: investigate its actual environment.
  4. Concealed crevices: record limits to what can be seen.

Illustrative geological cutaway, not a site photograph or measured section. Real systems may have several entrances and a much more complex geometry.

© 2026 ACP Consultants Ltd.
Original educational illustration

Keep geometry and seasonal function together

Caves, mines, tunnels and cellars can provide conditions buffered from rapid outside change. Entrance configuration, airflow and internal geometry influence that environment. A door, grille, infill or ventilation change can therefore matter beyond its immediate footprint.

The EUROBATS underground-site manual provides useful principles. However, it covers Europe, and its examples are not ready-made UK construction details. The current publisher catalogue lists the fifth edition from 2017; older catalogue pages still show earlier editions.

Start with existing plans and records, including any information held by the owner or established monitoring group. Then identify known entrances, connected chambers and gaps in the available information. Keep sensitive locations within the appropriate project team.

  • Describe existing and proposed use of the structure.
  • Record whether a plan is measured, historical or schematic.
  • Flag proposed lighting, heating, ventilation and water changes.
  • Identify access restrictions before arranging the survey.

Do not enter a cave, mine, tunnel or culvert to collect missing information for this checklist. The access plan must be agreed by competent people.

Seasonal use changes the question you need to answer

A winter count, an autumn activity record and a summer roost observation are different types of evidence. Therefore, a survey programme should explain which function it addresses and which questions remain open.

Winter shelter

A structure may provide suitable hibernation conditions, while some bats remain concealed. A visible count describes what the method could detect; it is not automatically a complete total.

Use the dedicated bat hibernation survey page for the winter assessment route and its limitations.

Summer roost use

Bridges and culverts can support summer roosts, including maternity use. Underground structures may also have seasonal roles beyond winter.

Therefore, a decision to schedule work in summer needs evidence about that particular structure. A calendar alone cannot establish a safe working period.

Autumn swarming

Swarming involves seasonal activity around some sites. For example, it can reveal use that winter inspections do not fully represent.

Parsons and colleagues sampled eight southern English cave, mine and tunnel sites over six years. Their study found seasonal differences in the bats recorded, illustrating why winter observations alone can miss part of a site’s role.

Transitional and intermittent use

A feature may be used at particular times or between other roosts. The project question is whether the evidence covers the relevant role and likely effect.

For example, a report prepared for a local repair may not answer the questions raised by a later tunnel conversion. Explain the difference before reusing it.

Choose survey methods around the decision, not a standard package

First establish the proposal and available records. Then decide what information is missing. The methods below can complement one another, but each has a different purpose and a practical limit.

Method selection and effort require a competent, site-specific rationale.
EvidenceWhat it can help establishWhat it cannot settle on its own
Records and drawingsPrevious use, survey history, geometry, connected habitat and proposed effects.Current absence, completeness of an old survey or the condition of an unseen feature.
Daytime assessmentPotential or confirmed features, visible evidence, access and coverage limitations.Every seasonal function or occupancy of concealed spaces.
Emergence observations and night-vision recordingWhether bats leave particular features, where coverage and conditions allow a defensible interpretation.Unobserved faces, hidden exits or winter use from a summer result alone.
Acoustic and movement evidencePatterns of activity and use around entrances or habitat connections, with appropriate identification review.A direct count of individuals, an exact roost location or confident species identification for every recording.
Winter or specialist seasonal workEvidence targeted at the relevant winter, swarming or other site-specific question.A generic clearance for unrelated works or a substitute for safe access and any necessary authorisation.

The report should explain why the chosen combination is suitable. It should also identify alternatives considered and the consequence of any unresolved limitation. See Bat Survey Guidelines and Methods Explained for the wider evidence framework.

Make coverage and uncertainty visible on the plan

Use the same feature references in the engineering drawings, survey notes, photographs and report. That makes it possible to follow a conclusion back to the area actually assessed.

For example, label the inlet and outlet of a culvert consistently. If observations covered one entrance, show that extent explicitly. Do not let a general asset label imply that every internal surface or connected opening was visible.

Similarly, record an obstruction as an obstruction. A blocked view beneath an arch or an inaccessible tunnel chamber is a limitation requiring interpretation. It is not evidence that the space contains no bats.

Keep observed facts, interpretation and recommendations separate. A useful report explains both the evidence and what it permits the project team to decide.

Review the construction sequence as well as the finished design

Ecological review works best when it follows the actual operation. Send the proposed preparation, treatment, temporary access and reinstatement sequence. Identify details that the contractor has not yet selected.

Repairing joints and fabric

Ask which gaps will be raked out, filled, injected or sealed. Show the work extent and any depth information available.

Where the scope changes after inspection, return the revised detail to the ecologist. A generic note to retain bat access cannot resolve an unspecified repair.

Lining or modifying a culvert

Provide the lining method, preparatory work, entrance details and expected change in the internal profile. Also show any temporary water management or lighting.

The team then needs to consider the affected fabric and habitat function together. Hydraulic and structural requirements remain part of the design discussion.

Restricting an underground entrance

Explain the reason for the restriction and the options being considered. Any security intervention must account for ecological use and the internal environment.

However, a standard gate detail is not evidence of suitability. Seek a justified design, responsibilities for maintenance and a way to check its outcome.

Changing the surroundings

Show vegetation removal, work compounds, site access and permanent or temporary lighting. Include effects beyond the asset boundary where relevant.

For watercourse work, supply the proposed changes in flow or water level. The ecological assessment can then address the habitat effect alongside the engineering proposal.

Ask whether a credible design change can reduce the impact

Further surveys should answer a defined question. Alongside that discussion, ask whether the proposed work can avoid an effect through a feasible change in extent, location or method.

For example, could an engineer justify a targeted repair instead of treating an entire face? Could equipment or a temporary light move away from an important entrance? Could a service route use an existing alternative? These are options to evaluate, not instructions to leave a structure unsafe.

Therefore, the ecologist and relevant designers need to review the revised proposal together. They should consider temporary works and indirect effects as well as the retained feature.

A useful outcome is a clear reason for the next step. That may be further evidence, a revised design, a licensing route or a combination. We aim to explain those choices, rather than leave you with an unexplained recommendation for more work.

Keep the entrance connected to suitable surrounding habitat

Lighting and the approach route

A structure can remain physically intact while its surroundings change. Therefore, review the entrance, bankside route and adjacent vegetation on the same plan as new lighting and temporary works.

A lighting note should identify the relevant receptors and the proposal to assess. Product labels or a lamp colour alone do not demonstrate that a sensitive route remains protected. See the detailed bats and artificial lighting guide for that design discussion.

Also consider how a route will function during construction. Temporary screening, access platforms or changes in site layout may need their own review.

Water, vegetation and maintenance

BCT’s waterways guidance highlights possible effects from changes in water flow, bankside vegetation and lighting. Therefore, include river or drainage works that sit outside the structure repair drawing.

Ask who will maintain any retained or new habitat, and how that task relates to inspection and safety requirements. A future maintenance plan should not conflict with the ecological feature the project is relying on.

For passage beneath transport infrastructure, EUROBATS discusses the importance of the crossing location and design. Do not assume that a nearby alternative opening provides an equivalent route.

Agree competence, access and permissions before fieldwork

Specialist structures often need several disciplines to work together. Clarify the ecological question first, then agree who can safely obtain the necessary evidence. However, access permission and ecological authorisation are separate requirements.

The ecological scope

  • Define the relevant seasonal questions and survey limits.
  • Check competence and any required licence for the proposed activity.
  • Plan how information will support design and reporting.
  • Identify specialist input where the site or method requires it.

The asset and access arrangements

  • Confirm ownership, operating restrictions and available records.
  • Identify structural, traffic, rail, water and access constraints.
  • Agree competent safety planning and emergency arrangements.
  • Keep responsibilities and permitted activities clear in writing.

In England, protected-species requirements can apply independently of planning permission. Elsewhere in the UK, check the relevant statutory authority. Our bat mitigation licence guide explains the England licensing discussion.

A practical briefing checklist for your structure

You do not need every answer before making contact. Send what is available, identify the gaps and distinguish confirmed details from options. The following headings make the first discussion more useful.

1 · The asset and its context

  • Asset reference, location and owner or operator.
  • Structure type and known construction history.
  • Current plans, photographs and inspection records.
  • Connections to water, vegetation, other structures or underground spaces.

2 · The proposed work

  • Marked-up extent and relevant drawing revisions.
  • Preparation, repair, lining or demolition method.
  • Materials, lighting and equipment where selected.
  • Temporary works, access and proposed sequence.

3 · Existing ecological information

  • Complete reports with dates, plans and limitations.
  • Relevant records and any monitoring history.
  • Known permissions, conditions or licence documents.
  • Changes since the earlier assessment.

4 · Constraints and decisions

  • Target programme and genuinely fixed constraints.
  • Known access and safety restrictions.
  • Design options still open for discussion.
  • The decision you need the next assessment to support.

For sensitive underground sites, use an agreed information-sharing route. A public web page or unrestricted drawing should not reveal confidential roost locations. Keep the technical project record complete while controlling its circulation.

Turn the evidence into a clear design and monitoring record

Make the report usable by the project team

Ask for a plan that relates findings to the work. It should identify assessed features, relevant habitat, survey coverage and material limitations. In addition, the conclusions should explain the project implications, including any further information required.

Keep an agreed revision record. If the contractor changes a material, repair extent, access arrangement or lighting proposal, identify who must review it before implementation.

Where measures are required, specify responsibilities, timing, checks and handover information. In other words, a general commitment to protect bats needs a practical route into the drawings and work instructions.

Define what a successful outcome would mean

Monitoring should test a stated objective, not simply confirm that a feature was installed. Depending on the project, the question might concern continued use, access, environmental conditions or habitat connection.

The EUROBATS conservation-evidence initiative records both successful and unsuccessful interventions. That supports a cautious approach to claims that a gate, grille or replacement feature will automatically deliver the intended outcome.

Agree how results will be reviewed and when corrective action would be considered. The post-development monitoring guide explains the wider approach.

Bridges and underground sites: frequently asked questions

Can modern bridges support bats?

Yes. Bats may use suitable joints, crevices or internal spaces in both old and modern bridges. However, construction age alone does not settle the question. Assess the actual features, their access and the proposed work.

Does bat activity under a bridge prove there is a roost?

No. Bats may pass beneath it or feed nearby without roosting in the structure. The assessment needs to distinguish movement and feeding from use of a particular roost feature.

Can a culvert support a maternity roost?

Yes, suitable culverts can support maternity use. However, that does not mean every culvert has the same function. Instead, the survey should investigate the particular structure and relevant season.

Does flooding rule out bat use?

A single observation of water levels cannot establish year-round absence. Therefore, provide any flooding history and identify uncertainty. The ecologist should consider the affected features, seasonal conditions and available evidence.

Is one winter visit enough to understand an underground site?

Not necessarily. It may provide useful evidence of visible winter use, but it does not automatically cover concealed bats or activity in other seasons. Survey scope depends on the site and the decision required.

What is autumn swarming?

It is seasonal bat activity around some sites, often underground entrances. Its timing and participants can differ from winter roost observations. Where relevant, it needs its own survey question and suitable evidence.

Can a detector identify the exact roost?

An acoustic record can support an assessment, but it does not by itself show precisely where a bat was roosting. Position, behaviour, visual evidence and recording limitations all affect the interpretation.

Can we repair or repoint around a potential feature?

A targeted approach may be worth assessing, but the details matter. The engineer and ecologist should review the affected fabric, preparation and temporary works before agreeing whether the option avoids an impact.

Would a bat-friendly grille solve an entrance problem?

Not automatically. The design needs to account for the site’s ecological use, access, environment and safety requirements. Therefore, a product description alone is not evidence that the proposed intervention is suitable.

Should I enter the culvert or tunnel to take photographs?

No. Use existing records and information obtained from safe, authorised positions. Do not enter a hazardous space, disturb a feature or handle bats to complete the briefing checklist. Access arrangements need competent planning.

Do maintenance works need ecological consideration without planning permission?

They can. Protected-species requirements are separate from planning permission. Explain the actual operation to a competent ecologist so the appropriate evidence, measures and any authorisation can be considered.

What should I send ACP first?

Send the asset location and reference, proposed work, available drawings, previous ecological reports and known access constraints. Include your programme and the decisions still open. We can discuss the information needed and any specialist input the project may require.

Sources, scope and how to use this guide

Research refreshed: 15 November 2026. This is a project-briefing and technical explanation guide. It does not provide an entry procedure, engineering specification or permission to work. The planning and licensing sources below apply to England. The three diagrams and reporting example are original teaching material, not ACP survey findings.

Collins (ed.), 2023; amended March 2024. Full existing reference reused, especially Chapter 5 on structures and Section 8.3 on swarming. The guidance informs professional judgement; it is not a universal survey package.

Current public guidance on roosts, river corridors, lighting, vegetation and changes to water flow. These functions need separate consideration.

The complete form was reviewed for its asset, feature, flooding and access records. It still cites the third-edition survey guidelines. Use current guidance for survey design; do not treat its older categories as a complete current specification.

Mitchell-Jones and colleagues: fifth edition, 2017, of the 2007 manual. Selected chapters on underground conditions, protection and management reviewed. European principles need local ecological and regulatory interpretation.

2024 guidance, including the underpass and culvert discussion. Passage suitability depends on the species, location and design; it does not establish roost occupancy.

Biological Conservation 111:63–70. Publisher abstract and bibliographic record reviewed; full paper not accessed. Eight southern English sites were sampled during 1995–2000. The study informs the seasonal distinction, not a present-day species total or prescribed survey effort.

Current HSE introduction checked. Avoid entry where possible; unavoidable entry needs competent assessment, controls and emergency arrangements. This guide provides no entry procedure.

Bring the asset information and the decision you need to make.

Tell us what is proposed and what remains uncertain. We can discuss the ecological brief, practical options and any specialist input needed.