Environmental consultancy for planning & development0330 236 7329hello@acp-consultants.com

BNG legislation · England

BNG legislation
& guidance

Understand the rules. Prepare the right evidence. Plan beyond permission.

BNG legislation in England sets a statutory objective of at least 10% biodiversity gain for development within the mandatory regime. First, the application must include biodiversity information. Then the biodiversity gain plan normally needs approval before development begins.

In practice, the route depends on the application history, exemptions, habitat evidence and local policy. This guide explains how those pieces fit together.

01 / The legal framework

What does BNG legislation require?

The Environment Act 2021 introduced the mandatory BNG framework. For example, the principal BNG legislation for ordinary planning permissions in England sits in Schedule 7A to the Town and Country Planning Act 1990. In addition, regulations supply further rules on exemptions, procedure, registration and special cases.

Planning permission within this regime is subject to a statutory biodiversity gain condition. The biodiversity gain objective is met through the permitted combination of on-site biodiversity value, registered off-site gains and statutory credits.

The 10% objective measures habitat value through the statutory biodiversity metric. Specifically, the calculation accounts for habitat type, area or length, condition and delivery risks. As a result, the gain target reflects the ecological quality of the proposal.

Find the right BNG legislation and guidance

Legislation

What it establishes

The legal framework, gain condition, exemptions and statutory procedures.

Where to look

Schedule 7A and the relevant regulations, including any commencement and saving provisions.

National guidance

What it explains

How the planning process and technical requirements should operate in practice.

Where to look

Planning Practice Guidance, Defra guidance and Natural England’s technical material.

Local policy

What it adds

Relevant development-plan policies, local ecological priorities and potentially a higher gain target.

Where to look

The adopted local plan, supporting guidance and the applicable Local Nature Recovery Strategy.

Project evidence

What it demonstrates

Why the chosen route applies and whether the proposal can deliver its commitments.

Where to look

Survey reports, habitat plans, metric files, planning history, legal documents and management plans.

Read these sources together: legislation establishes the requirements, national guidance explains the procedure, and local policy and checklists identify the evidence for your site.

02 / Dates & changes

When did BNG legislation take effect?

Start with the relevant application date and planning route. Because transitional provisions connect earlier permissions to later submissions, keep the full planning history alongside these milestones.

  1. Major development

    Mandatory BNG began for relevant planning applications, subject to exemptions and transitional arrangements.

  2. Small development

    The temporary exemption for small development ended. However, the applicable route still depends on the proposal and its history.

  3. Amended rules

    New exemptions and a revised hierarchy for non-major development took effect, with specific saving provisions.

  4. NSIP commencement

    The separate mandatory regime applies to relevant development consent order applications made on or after this date.

Planning milestones · © 2026 ACP Consultants

How did BNG legislation change in August 2026?

The 2026 amendment regulations introduced an exemption for development on sites of 0.2 hectares or less, provided there is no impact on on-site priority habitat. In addition, a separate temporary-development exemption has detailed conditions.

These new routes apply to qualifying applications made on or after 6 August 2026. By contrast, earlier applications follow the relevant transitional and saving provisions. The regulations also removed the previous self-build and custom housebuilding exemption for new applications, while preserving it for qualifying earlier applications.

Use our BNG exemptions and thresholds guide for the full route tests, evidence and exemption-statement support.

Choose the correct consent framework

Different routes, coordinated habitat evidence
CheckOrdinary planning permissionNationally significant infrastructure
Legal frameworkTown and Country Planning Act 1990, Schedule 7A.Planning Act 2008, Schedule 2A, and the relevant biodiversity gain statement.
BoundaryAssess the on-site baseline within the planning application boundary.The BNG boundary may differ from the order limits. Include negatively affected habitats and habitats contributing to the gain.
Plan sequenceGain plan after permission; overall and phase plans for qualifying phased development.Outline gain plan with the DCO application, followed by the required updated or phase plans before commencement.

The mandatory NSIP framework applies to relevant DCO applications made on or after 2 November 2026. Check the relevant biodiversity gain statement and consent requirements.

03 / The planning process

BNG guidance for each planning stage

Start the evidence before submission. Then carry the agreed baseline and delivery commitments through the decision, gain plan and habitat management documents.

01

Application

First, explain whether BNG applies. Then provide the required baseline information and enough detail to assess the proposal.

Application evidence ↓
02

Decision

Resolve the feasibility of the gain strategy, relevant policy matters and the mechanisms needed to secure delivery.

Decision-stage checks ↓
03

Before starting

Obtain approval of the biodiversity gain plan, or the relevant phased plans, before the applicable commencement trigger.

Gain-plan requirements ↓
04

Delivery

First, create or enhance the agreed habitats. Then manage, monitor and report against the secured commitments.

Long-term duties ↓

Application evidence: establish the baseline

If you consider the proposal exempt, state the reason and provide proportionate evidence. If mandatory BNG applies, the national minimum information includes:

  • A statement that the biodiversity gain condition would apply.
  • The pre-development biodiversity value and completed metric calculation, including the metric’s publication date.
  • The proposed relevant date, with reasons if an earlier date is proposed.
  • Information about relevant habitat degradation and the earlier value where the statutory rules apply.
  • A description of any irreplaceable habitat.
  • A scaled plan showing the habitats, with north indicated.

Also check the council’s current validation list for additional proportionate information. By comparison, the final gain plan follows permission. At application stage, a credible draft strategy helps demonstrate that the proposed layout can deliver its biodiversity commitments.

Our planning validation checklist helps organise the submission documents.

Decision stage: coordinate delivery

Throughout the process, the metric, drawings and ecological evidence work together. The planning authority must be able to assess the proposal, including relevant ecological effects and policy compliance.

In particular, check that the gain strategy works with access, drainage, services, landscape design and ownership. Where significant on-site gains need protection, identify the planning condition, obligation or conservation covenant that will secure them.

Keep the habitat plan and layout coordinated

For example, a habitat area may become a drainage compound or utility corridor during design. Update the habitat plan and metric together. Reconcile drawing revisions before the decision and again before submitting the gain plan, so every claimed habitat has a deliverable location.

Also identify responsibilities early: who supplies the ecological evidence, who negotiates the legal mechanism, and who will manage the habitat after construction?

Before commencement

The biodiversity gain plan connects permission to delivery

For a permission subject to the condition, submit the plan after permission is granted and obtain approval before development begins. Approval of the final plan satisfies this pre-commencement requirement.

Ultimately, the final package must explain how the biodiversity gain objective will be met. Depending on the scheme, this includes the completed metric, final habitat proposals, secured management arrangements, registered off-site allocations and evidence of statutory credit purchases.

Use the official gain-plan submission guidance and our biodiversity gain plan service guide to identify the required attachments.

BNG planning illustration showing homes, retained hedgerows, meadow habitats and a rain garden

Evidence that works together

One coordinated plan,
from design to delivery

Connect the site evidence, development layout and habitat commitments through a clear record of decisions.

  1. Survey & mapOne agreed boundary and habitat baseline.
  2. Design & calculateMatching revisions of the layout, habitat plan and metric.
  3. Secure & manageClear responsibilities, targets and monitoring.
Planning evidence & habitat delivery · © 2026 ACP Consultants

Allow time for gain-plan approval

For an ordinary planning permission, the earliest submission date is the day after permission is granted. The authority normally has eight weeks to determine the plan, unless a different period is agreed.

If the authority refuses the plan or does not decide it within the applicable period, a section 78 appeal may be available. The normal appeal limit is six months from the decision or expiry of that period. First discuss outstanding evidence and the timetable with the authority. Approval remains necessary before the relevant commencement trigger.

Bring specialist evidence into the same submission

First, the ecologist leads habitat classification, metric inputs and ecological targets. Where a scheme affects a river, coordinate the required river condition assessment with geomorphology, drainage or flood-risk specialists as the proposal requires. Meanwhile, a water engineer can inform levels, flows and constructability. The relevant ecological assessor supplies the habitat-condition evidence.

Then reconcile those inputs with the landscape plan, access, utilities and HMMP. Record the responsible author, survey date, drawing revision and outstanding assumptions for each input.

04 / Technical evidence

Technical BNG guidance: baseline, metric and habitats

Follow the statutory BNG metric guidance

Use the statutory biodiversity metric for mandatory BNG. It succeeded Biodiversity Metric 4.0 and has its own published rules, calculation tools and supporting guidance.

The official metric collection provides the tools, user guides and version history. Therefore, record the version used and check its rules. Alternatively, a simplified Small Sites Metric is available where its eligibility conditions are met.

Assess area habitat units, hedgerow units and watercourse units separately, meeting the relevant target and trading rules in each account. See our guide to biodiversity unit calculations.

Establish the baseline date and site history

The relevant date is normally the planning application date, although an earlier date can be agreed. Therefore, use surveys that support the habitat value at the applicable date. Also review older reports against current site conditions.

Schedule 7A distinguishes two cases where activities have lowered habitat value:

  • On or after 30 January 2020: paragraph 6 covers activities carried out otherwise than in accordance with planning permission.
  • On or after 25 August 2023: paragraph 6A covers activities under another planning permission where that development has not begun, or has not been completed, on the relevant date.

Where the statutory conditions apply, use the value immediately before those activities. Under paragraph 6B, insufficient evidence requires the highest value reasonably supported by the available evidence.

Therefore, assemble dated surveys, photographs, aerial imagery, management records and permission documents. Record which provision applies and how the earlier habitat value was established.

Irreplaceable habitats and wider ecology

Irreplaceable habitats, including ancient woodland and ancient or veteran trees, need separate consideration. Their loss follows a bespoke compensation route under the irreplaceable-habitat provisions, alongside the relevant planning policy tests.

The government’s irreplaceable-habitat guidance explains the modified requirements, impact minimisation and bespoke compensation arrangements.

Also coordinate BNG with protected-species law, designated-site requirements and other ecological planning duties. Each has its own evidence and decision tests, which the proposal must satisfy.

05 / Permission history

How BNG legislation applies to different permissions

First, establish the route under BNG legislation from the complete permission history. Then review each new submission alongside its original application, conditions and approved plans.

Outline permissions

What to establish

Identify whether the original outline permission is within the mandatory regime. Then reserved matters supply the detail under that outline permission.

Practical consequence

The detailed layout must remain consistent with the applicable gain strategy. Therefore, check the outline conditions, parameters and any approved plans before changing habitat areas.

Phased development

What to establish

Check whether the permission is phased for the statutory BNG provisions. An overall biodiversity gain plan and separate phase plans are required under the modified framework.

Practical consequence

The overall plan precedes commencement of development; each phase plan precedes its phase. Accordingly, allocate habitat delivery and dependencies clearly. Use the official phased-development templates.

Section 73 variations

What to establish

Check the original application and permission dates, the variation and the relevant transitional or saving provisions. Consequently, a section 73 permission may need an updated gain plan.

Practical consequence

For the new site-size and temporary routes, check both the original application and original permission dates. The section 73 saving provisions preserve the earlier position where either predates 6 August 2026.

Keep a permission history schedule

Record the application reference, submission date, decision date, permission type, amendments and approved drawings. This short schedule can prevent the wrong exemption, baseline or gain-plan route being carried through a project.

Worked permission-history example

A later variation still needs the earlier dates

For example, consider an illustrative 0.18-hectare housing site with no impact on priority habitat. The original application was made on 1 August 2026, permission was granted on 15 September, and a section 73 application follows in November.

In this example, the original application predates 6 August. Therefore, the saving provision prevents the section 73 permission from gaining the new site-size exemption, even though the variation is submitted later.

  1. 01
    1 August · original application

    Record the date the application was made.

  2. 02
    15 September · permission

    Keep the decision notice and approved plans.

  3. 03
    November · section 73

    Apply the saving provision to the full history.

Next step: review the existing gain-plan position and changes to habitat delivery with the planning adviser and ecologist. A fresh application has its own legal route and must be assessed separately.

06 / National rules, local decisions

Check the council’s policy as well as the 10% minimum

Alongside the statutory minimum, an adopted local-plan policy can seek a higher percentage where justified. In addition, other policies may address habitat networks, species measures and ecological information.

Check the adopted policy wording, supporting documents and validation list separately. Then identify any relevant local nature-recovery priorities. Use the adopted policy itself to confirm the development types, thresholds and qualifications that apply.

  • Which policy applies to this development type?
  • Is the stated percentage adopted policy or emerging policy?
  • What evidence does the council ask for at this stage?
  • How do the proposals respond to local habitat priorities?
  • Are separate ecology measures required even if mandatory BNG is exempt?

The delivery hierarchy also depends on the applicable rules

Major development

The statutory hierarchy prioritises avoidance and mitigation for the relevant higher-distinctiveness habitats, then on-site enhancement and creation, registered off-site gains and finally statutory credits.

Therefore, record the design choices and the reasons for using each delivery option. In turn, this evidence supports the gain plan and any off-site unit allocation.

Non-major development

Under the hierarchy amended from 6 August 2026, on-site enhancement or creation and registered off-site gains sit at the same level for non-major development. However, statutory credits remain below those options.

Check the permission’s history and saving provisions, alongside the separate habitat and species protections that apply to the site.

For the detailed sequence and evidence, see our biodiversity gain hierarchy guide. Use the current national rules if an older local document describes a superseded procedure.

07 / Beyond permission

What does the 30-year commitment mean?

Registered off-site gains and significant on-site habitat enhancements need long-term security. First, establish the legal mechanism, maintenance period and start trigger for each part of the strategy.

For ordinary planning permissions, maintain significant on-site enhancements for at least 30 years after development is completed. By comparison, registered off-site gains run from completion of the habitat enhancement works.

For NSIPs, however, all on-site habitat creation and enhancement contributing to BNG is significant. Its minimum 30-year maintenance period starts when those habitat works are completed. Record the applicable trigger explicitly in the legal agreement or consent requirement.

An HMMP explains habitat creation, management, monitoring and corrective action. Then align it with the planning condition or legal agreement that secures delivery.

For habitat choices and management responses to drought, flooding and changing conditions, see our BNG and climate resilience guide. Where EIA applies, use our BNG and EIA guide to coordinate the wider assessment.

On-site gains under ordinary planning permission

These can be secured through a planning condition, a section 106 planning obligation or a conservation covenant, as appropriate. In each case, the authority assesses significance in the context of the proposed enhancement.

Agree the significance of the proposed enhancements with the authority and keep the habitat strategy, metric and securing mechanism consistent.

Registered off-site gains

Off-site habitat gains need a qualifying legal agreement, registration and allocation to the development. Therefore, obtain the register and allocation evidence that connects the secured gains to this development.

Read our comparison of section 106 agreements and conservation covenants. At the same time, coordinate legal drafting with the ecological delivery documents.

08 / Practical planning tool

Build your BNG evidence checklist

Use this free planner alongside the BNG guidance above. Select your permission route, current stage and delivery approach. Then get an organised starting checklist, including the questions to resolve before the next milestone.

Use the checklist to organise documents and questions for your planning team. Your selections stay in this page until you leave or reset it.

BNG planning-stage evidence planner · © 2026 ACP Consultants

09 / Frequently asked questions

BNG legislation,
in practice

Use these answers alongside the BNG legislation and guidance linked in our source notes.

Is biodiversity net gain a legal requirement across the UK?

In England, BNG legislation provides a mandatory framework. By contrast, Scotland, Wales and Northern Ireland have their own planning and biodiversity arrangements. Therefore, follow the requirements for the nation where development is proposed.

Does a planning permission have to list the biodiversity gain condition?

The statutory condition is deemed to apply to relevant permissions, including where it is absent from the numbered conditions. Establish the position from the legislation, decision notice and application history.

Can I start work while the biodiversity gain plan is being considered?

Where the statutory condition applies, obtain approval of the relevant gain plan before commencement. Then confirm that the other pre-commencement conditions have also been met before starting the works.

Is 10% enough if the council asks for 20%?

First, check the adopted policy and its application to your proposal. The national statutory minimum and a justified higher local-plan requirement can both be relevant. Therefore, ask the planning team to identify the policy basis for the percentage.

When can a small site use the Small Sites Metric?

Where BNG applies, the Small Sites Metric is available when the proposal meets its development and habitat eligibility rules. First establish the exemption position, then choose the appropriate metric for the habitats and development.

What ecological evidence supports an exemption?

Provide proportionate evidence for the specific exemption criteria. Also check the evidence needed for protected species, designated sites, wider ecological impacts and local policy. Where the site evidence supports the route, ACP can then prepare an exemption statement.

How do purchased units fit into the biodiversity gain plan?

Registered off-site gains can form part of the delivery strategy. The gain plan explains the overall position and identifies the gains allocated to the development. Therefore, confirm the register entries, allocation references and metric treatment before submitting the plan.

Who should check an older or varied planning permission?

First, coordinate the review between the project’s planning adviser, ecologist and legal adviser where needed. The permission history determines the procedural route; the ecology evidence determines the habitat position. Together, these establish the requirements for the specific proposal.

How long does the council have to decide a biodiversity gain plan?

The normal determination period is eight weeks, unless a different period is agreed. Refusal or non-determination can provide a section 78 appeal route, normally within six months. Agree a timetable with the authority and obtain approval before the relevant commencement trigger.

When does the 30-year period begin for an NSIP?

For on-site habitat creation and enhancement contributing to NSIP BNG, the minimum maintenance period begins when the habitat works are completed. All such contributing creation and enhancement is significant. Align the HMMP with the consent requirements and legal agreement.

Discuss your BNG requirements

The right evidence.A clear next step.

Tell us the site location, planning stage and the BNG requirement you need to resolve.

  1. Your planning route

    Share your proposal, application dates and any earlier permissions.

  2. Your next milestone

    Tell us about the council’s request, gain plan or delivery question.

  3. Your supporting evidence

    Start with the information you have. If a review is appropriate, we can discuss how to share supporting documents securely.

Source notes & scope

Follow the primary sources

This guide covers England’s ordinary planning BNG framework and identifies the separate NSIP regime. It draws on the legislation and official guidance below. Project requirements depend on the permission history, site evidence and applicable local policy.

Legislation and planning procedure

  1. Town and Country Planning Act 1990, Schedule 7A — statutory gain condition and objective.
  2. Planning Practice Guidance: biodiversity net gain — application information, procedure, transitional cases and phased development.
  3. Biodiversity gain amendment regulations 2026 — changes effective from 6 August 2026 and saving provisions.
  4. Submit a biodiversity gain plan and phased-development templates — final plan requirements.

Technical and delivery guidance

  1. Statutory biodiversity metric tools and guides — calculation tools, eligibility and technical rules.
  2. Irreplaceable habitat guidance — modified requirements and compensation.
  3. On-site gains, off-site gains and HMMP guidance — security, management and monitoring.
  4. BNG for nationally significant infrastructure projects — separate scope, statements and commencement.
  5. Legal agreements for BNG — securing mechanisms and maintenance start dates.
  6. Guildford Borough Council’s biodiversity guidance and adopted Policy P7 — local-policy example.

Prepared by ACP Consultants. Sources reviewed on . Follow the provisions relevant to your application date and permission history.