Environmental consultancy for planning & development0330 236 7329hello@acp-consultants.com

Westminster / Local planning guide

Biodiversity Net Gain in Westminster

Biodiversity net gain in Westminster needs a clear site strategy, from Policy 38 and urban habitats to Gain Plan approval and long-term monitoring.

From Paddington and Maida Vale to Marylebone, Soho, Mayfair and Victoria, dense development brings different constraints. ACP coordinates habitat surveys, metric assessments and delivery evidence with your planning and design team.

Reviewed 6 November 2026 · City Plan adopted January 2026 · Environment SPD February 2026 · Monitoring schedule May 2026

Current law / adopted policy / site evidence

Does your Westminster proposal need statutory BNG?

Qualifying planning permissions normally require at least 10% biodiversity gain. However, determine the legal scope before choosing a metric route or assuming the project needs off-site units.

Check the current exemption tests

For relevant applications from 6 August 2026, sites of 0.2 hectares or less can qualify for exemption. However, this does not cover development affecting on-site priority habitat. Assess the whole red-line site and the actual habitat effects.

Householder, de minimis and temporary-development exemptions have separate tests. Meanwhile, the general self-build exemption ended for relevant new applications. Earlier permissions and section 73 cases need transitional checks.

Keep ecology and statutory gain distinct

An exemption from the statutory gain condition does not remove every ecological planning requirement. For example, Policy 38 and protected-habitat requirements, protected-species law, trees and river-corridor policies may still affect an exempt scheme.

Conversely, an in-scope proposal needs suitable habitat calculations even without an identified protected-species issue. Therefore, explain the legal route and the ecological assessment separately in the site brief.

Check the current government exemptions and our BNG exemptions guide. The statutory biodiversity metric tools were updated on 10 November 2026. Government guidance permits other published statutory-tool versions; the old non-statutory Defra Metric 4.0 is different. Also check Small Sites Metric eligibility separately; site size alone does not establish it.

National law / London Plan / Westminster City Plan 2026

Which Westminster policies shape the application?

Westminster City Council is the local planning authority. First, confirm the red-line boundary and relevant site policies. The City Plan adopted on 21 January 2026 replaced the 2021 version. It sits alongside the adopted London Plan.

Apply the adopted policy to the actual proposal
Policy or evidencePractical meaning
Policy 38 — Green Infrastructure

Clauses F and G address ecological protection and feasible biodiversity gain. Also consider green roofs, walls, rain gardens and habitat links. However, national law determines statutory BNG scope; an exemption does not remove every ecological duty.

Policy 38 — Royal Parks and trees

Clauses C–E protect open-space and park functions, while H/I address trees. Therefore, consider ecology, amenity and historic value together. Not every mature tree is an irreplaceable habitat.

Policy 35 — Waterways and Waterbodies

Protect relevant Thames foreshore, canal and waterbody features. Also assess wildlife links and waterside design. The required metric module depends on the actual feature and impact.

Policies 37 and 39 — Light and water

Address sensitive lighting, flood risk and relevant drainage requirements. For example, habitat planting can complement SuDS. However, flood performance does not establish biodiversity condition.

Policies 42, 43 and 44 — Design, retrofit and heritage

Coordinate habitat proposals with design, Retrofit First and heritage requirements. Also test structural capacity, fire safety and maintenance. A roof or wall may have constraints beyond ecology.

London Plan G5, G6 and G7

Apply strategic greening, biodiversity and tree requirements alongside local policy. In particular, keep the Urban Greening Factor calculation separate from habitat-unit gain.

Read the adoption record and January 2026 City Plan. Policies 8–11 cover four allocated sites, including St Mary’s Hospital and Westbourne Park Bus Garage. Check applicability against the site boundary.

The New City Plan remains emerging

The council’s current New City Plan page invites consultation responses before 11 December 2026. This follows its July commencement and timetable notices. However, that consultation does not replace the adopted January plan or establish a binding new 30% BNG target.

Compare the requirements →

Statutory minimum / local aspiration / urban greening / monitoring

Does Westminster require 10% or 30% biodiversity gain?

The February 2026 Environment SPD encourages ambition beyond the national minimum. However, an aspiration, a greening score and a council contribution are different requirements. Use the following comparison before setting the project brief.

Four figures that should not be treated as one target
RequirementMeaning for the project
At least 10% statutory BNG

This is the normal national minimum for qualifying permissions. First check exemptions and transitional rules. Then demonstrate the appropriate metric calculation, delivery and formal Gain Plan approval.

30% local aspiration

Environment SPD §215 asks developers to aspire to 30% wherever possible. It is not a universal binding minimum. Similarly, discussion of a higher target in a future plan does not establish adopted policy.

UGF 0.4 or 0.3

London guidance generally uses 0.4 for predominantly residential and 0.3 for predominantly commercial major development, with exclusions. This measures weighted green surfaces. Therefore, UGF 0.4 does not mean 40% habitat gain.

A monitoring contribution

Westminster publishes three monitoring bands for relevant long-term gains. These fund council review through the legal agreement. However, payment does not itself deliver habitats or purchase biodiversity units.

Use Environment SPD §§190–215, GLA UGF guidance and the council monitoring schedule. Also document which requirements apply, rather than quoting every figure as a mandatory threshold.

A practical Westminster briefing asset

Seven checks before finalising the site strategy

Use these checks to connect planning, ecology and design work. They bring Westminster’s policy, heritage and monitoring questions into the same brief while keeping the legal tests clear.

  • Record the red-line area, proposed works, submission date and priority-habitat effects. Then check the current exemptions and transitional rules before choosing a statutory metric route.

  • Use City Plan 2026, Policy 38 and relevant waterways, lighting, flood, design and heritage policies. Also check the exact boundary of any site allocation or protected feature.

  • Obtain appropriate records, UKHab and condition evidence. Then scope species and tree work where needed. An urban address does not establish a zero-value baseline or the absence of protected wildlife.

  • Coordinate soil, substrate, lighting, drainage, structural and maintenance requirements. Also calculate UGF separately where applicable. Keep proposed habitat condition realistic for the site.

  • Provide the required biodiversity statement, completed baseline metric and scaled habitat plan. Explain any exemption. Use the council’s dated N9 and L5 requirements alongside current law and the 2026 SPD.

  • Where the gain condition applies, obtain Gain Plan approval after permission and before commencement. Also verify registered units, legal allocation and any phased delivery requirements.

  • Identify relevant significant gains, habitat parcels and legal responsibilities. Then confirm the council monitoring tier, habitat care budget and reporting programme. Keep these separate from survey and unit-purchase costs.

Begin with the boundary and available drawings. This checklist helps scope the work; it does not determine an exemption or replace field evidence. For the wider sequence, see our BNG process guide.

N9 biodiversity statement / L5 ecology / formal Gain Plan

Submit the evidence at the correct planning stage

Westminster’s linked full validation list dates from March 2024. It distinguishes the biodiversity statement from a wider ecology report. However, some policy numbers and metric references predate current law and the adopted 2026 City Plan.

Use local validation alongside current national requirements
Stage or documentPractical action
N9 — Biodiversity Net Gain Statement

For an in-scope application, provide the required statement, baseline metric and scaled existing-habitat plan. Also address the baseline date, degradation and irreplaceable habitats where relevant. Explain and support a claimed exemption.

L5 — Biodiversity Survey and Report

Assess relevant SINCs, priority habitats, species and other ecological features. The list includes proximity to woodland, water and connected trees, plus sensitive building and lighting works. However, a 50m screening example is not a blanket statutory-metric rule.

Design-stage delivery evidence

Use competent survey data and consistent habitat parcels across drawings and calculations. Also assess tree retention, roof design and practical management. An early draft HMMP can help show that significant gains are deliverable.

Post-permission Gain Plan and management

The formal Gain Plan needs approval before commencement where the condition applies. Include final metric and habitat plans, relevant HMMP and recorded off-site allocations. Also address overall and phase plans where the permission requires them.

Check the current validation gateway, March 2024 list and council BNG requirements. Pair these dated local sources with the national minimum information and 2026 Environment SPD. Older “Policy 34” or “Metric 3” wording should not guide a current statutory calculation.

Royal Parks / canals / Thames foreshore / urban habitats

Read the ecological context before choosing an intervention

GiGL’s February 2026 factsheet records 33 SINCs covering 521.8 hectares, or 23.7% of Westminster. It also maps 67.5 hectares of priority habitats. These source-dated totals describe the borough; they do not establish the habitat value of a development parcel.

Royal Parks and historic landscapes

Regent’s Park, Hyde Park, Kensington Gardens, The Green Park and St James’s Park combine grassland, trees, water and other habitats. They also have distinct ownership, management and heritage contexts. Therefore, assess the actual boundary and potential effects.

A nearby development may need sensitive lighting, tree or species evidence. However, proximity alone does not prove that the plot contains a protected habitat. Nor does a park’s designation make its land available for off-site unit sales.

Little Venice, Paddington Basin and the canal

The Grand Union Canal and connected waters bring aquatic, bank and movement-corridor issues. Policy 35 and lighting policy can affect waterside design. First identify the waterbody, riparian features and actual development impacts.

Then use the correct metric and survey approach. A canal-side postcode does not automatically require every river assessment. Also coordinate planting, water quality, access and management with the relevant landowner and approvals.

The Thames, Embankment and Victoria

Tidal foreshore and waterfront proposals can involve ecology, flood defences, navigation and public access. For example, lighting and bank works may affect habitat functions beyond the red line. Assess the actual proposal and impact pathway.

Keep area, hedgerow and watercourse accounts distinct where applicable. Also check consents and flood infrastructure before promising habitat creation. A neighbouring basement or roof scheme should not inherit every waterfront requirement automatically.

Soho, Mayfair, Marylebone and North Paddington

Dense streets, estates, gardens and historic courts can contain trees, planted roofs and fragmented habitat links. Meanwhile, North Paddington and Westbourne Green illustrate opportunities to improve nature access and green connections. Survey the actual starting condition.

For roofs and walls, test substrate, water, structural capacity, fire safety and future maintenance. Then align planting with realistic habitat targets. Bird and bat features can support wildlife without automatically generating area-habitat units.

Read the GiGL February 2026 factsheet and Royal Parks habitat guidance. Some council documents contain inconsistent SINC area figures. This guide uses the dated GiGL source, without trying to reconcile those figures. Obtain current mapping and licensed records for a site decision.

Published London LNRS / Westminster action programme

Connect mapped priorities with practical habitat management

London’s Local Nature Recovery Strategy was published in March 2026. Westminster also has a September 2024 Greening and Biodiversity Strategy and a 2025 Action Plan. These provide useful context, but their maps and projects serve different purposes.

Use the relevant LNRS measures

Overlay the site with current habitat and nature-recovery evidence. Then test strategic significance against the actual habitat, measure and metric rules. A location anywhere in Westminster does not justify an automatic higher score.

Public GIS data updated in September 2026 omit some licensed information. Therefore, obtain further records where needed. An opportunity area is not a new statutory designation, planning consent or registered stock of biodiversity units.

Make urban habitats maintainable

Westminster’s strategy addresses connected green spaces and uneven nature access. For example, tree soil volumes, roof substrate and irrigation can determine whether a design survives. Also plan monitoring and remedial work from the outset.

The council reports more than 60 greening projects initiated since September 2023. “Initiated” does not mean that every project is complete or legally secured as BNG. Use the programme as local context, then specify the obligations for your development.

Use the published London LNRS, public spatial data and Westminster strategy and progress reports. Also keep UGF, habitat units, species measures and nature-access improvements distinct in the evidence.

Biodiversity Duty Report / January 2023–December 2025

What do Westminster’s first BNG figures show?

The council’s 2026 report records 29 BNG-liable applications received during its first reporting period. However, no formal Gain Plans had been approved by 31 December 2025. These historical figures distinguish planning progress from habitat delivery.

Understand the stage before drawing conclusions
Dated evidenceImplication for applicants
29 applications; no approved Gain Plans at the cut-off

The report describes the position up to December 2025. It does not establish that no plans were approved later. Therefore, check an individual application’s current register and condition status.

Different planning and submission stages

The report records two incomplete Gain Plan submissions, 13 permissions awaiting a plan and 12 undetermined applications. One application was refused and one withdrawn. Planning permission alone does not discharge the gain condition.

Likely on-site and off-site delivery

Of 27 live projects, 17 were expected to use on-site delivery and eight off-site delivery; two had no declared route. These are anticipated strategies, not proof of purchases, allocations or established habitats.

One proposed in-borough off-site gain

The report also mentions a local proposal and exploration of further options. However, this does not establish registration, remaining units or availability to another buyer. No monitoring reports had been reviewed in that first period.

See Biodiversity Duty Report §5.2. Its references to forthcoming policy and monitoring fees reflect the reporting period. The City Plan, Environment SPD and monitoring schedule were subsequently adopted or published during 2026.

Committee evidence / community greening / clear project status

Learn from the planning conditions and delivery context

Westminster’s public records show how biodiversity can interact with heritage, trees and constrained landscapes. However, a planning decision, a habitat-management commitment and an established ecological outcome are different forms of evidence.

St James’s Park memorial proposal

On 7 April 2026, the planning committee considered the National Memorial to Queen Elizabeth II. The minutes record a unanimous resolution to grant conditional permission and listed building consent, including an amendment to Condition 16.

That condition addressed Gain Plan evidence, a minimum 10% metric result, long-term management, off-site allocation and tree-transplanting aftercare. The committee record does not itself establish a later approved Gain Plan or successful habitat delivery. No ACP involvement is claimed.

Westbourne Green and North Paddington

The duty report records the Westbourne Green Micro-Forest opening in February 2025 with 426 native trees. It also describes staged canalside and green-space work in North Paddington, including drainage and access improvements.

These are useful examples of urban planting and community nature provision. However, they are not evidence of available BNG units or an ACP project. Read the council’s project descriptions and distinguish completed work from proposed later phases.

Metric shortfall / verified stock / legal allocation

How can a Westminster project source off-site units?

Off-site delivery may be relevant where the project cannot provide suitable gains on site. For qualifying non-major development, the hierarchy changed in August 2026: on-site creation or enhancement and off-site delivery can sit at the same level, with retention prioritised and statutory credits last.

Check availability beyond registration

Use the official biodiversity gain-sites register to identify the legal parcel and recorded allocations. Then obtain current written confirmation of habitat types, unallocated units, operator, price and reservation terms. Registration alone does not establish stock.

No buyer-ready Westminster package and price was independently verified for this guide. That does not prove that none exists. Similarly, council discussions with landowners, Royal Parks projects and LNRS opportunities should not be promoted as units for sale.

Match the deficit and complete allocation

Apply habitat trading and spatial-risk rules to the actual area, hedgerow or watercourse deficit. Also use suitable strategic-significance evidence. The nearest offer may lack the right habitat, while distance can affect the quantity needed.

Complete the required allocation to the development and include the evidence in the Gain Plan. Then check legal security, management, monitoring and remedies for qualifying long-term gains. A monitoring payment or conservation donation does not itself purchase compliant units.

Use current national hierarchy guidance and our HMMP guidance. Government statutory biodiversity credits are a separate last-resort route, not a private habitat-bank price.

Council schedule / 27 May 2026 / excluding VAT

What does biodiversity net gain in Westminster cost?

Westminster publishes a one-off contribution for council review of relevant long-term habitat gains. It is secured through the appropriate section 106 agreement. First establish whether the monitoring requirement applies; the fee is not automatic for every exempt development.

Council monitoring bands: apply the complete criteria
Monitoring bandPublished qualifying criteria
Low — £8,108 excluding VAT

All criteria must apply: red-line site area no more than 0.5 hectares; no more than three monitored habitat parcels; and no creation of high- or very-high-distinctiveness habitat.

Standard — £10,009 excluding VAT

The scheme does not meet the low band, and all standard criteria apply: area no more than two hectares; no more than ten monitored parcels; and no high- or very-high-distinctiveness habitat creation.

High — £13,113 excluding VAT

Any criterion triggers this band: area greater than two hectares; at least eleven monitored parcels; or creation of high- or very-high-distinctiveness habitat. Therefore, a small site can still fall in the high band.

A monitored parcel is a separate post-development metric row with biodiversity value above zero. The council treats private-dwelling vegetated gardens separately. Confirm the published schedule and actual legal agreement when budgeting.

Check significance and management scope

The council proposes treating newly created or enhanced on-site habitat as significant, apart from private-dwelling vegetated gardens. This reflects Westminster’s urban context. However, confirm the actual habitat, legal trigger and project-specific securing arrangements.

For example, a 0.3ha in-scope scheme with two ordinary monitored parcels may meet the low criteria. Creating high-distinctiveness habitat can instead trigger the high band. These illustrate the published rules; they are not individual council quotations.

Separate the remaining budget items

The monitoring contribution covers council review over the stated 30-year period; it is not an annual charge to multiply by 30. Also budget for professional surveys, metric and Gain Plan work, legal agreements and physical habitat care.

The April 2026 national schedule lists £309 for the relevant non-householder condition-approval route. This is separate administration. Any purchased units require a current habitat-specific quotation, with allocation and management evidence.

Our BNG costs guide explains the wider budget. Also check the national planning fee schedule before submission. A proposed future fee is not in force merely because it appears in a consultation.

Proportionate surveys / coordinated design / practical delivery

Discuss biodiversity net gain in Westminster with ACP

Send the site address, red-line plan, intended works and planning stage. Also share any existing ecology, tree, roof, landscape or metric information and council comments. Flag known heritage, structural, waterway or timing constraints so the scope addresses the real project.

Our BNG assessments and UKHab baseline surveys establish habitat evidence. Biodiversity Gain Plan support connects the final design with delivery. Speak to our BNG consultants about a proportionate evidence programme.

The London BNG guide explains the strategic context. Nearby guides include Camden, Kensington and Chelsea, Lambeth and the City of London. However, neighbouring policies and monitoring fees are not interchangeable. Confirm the responsible authority for the actual red-line site.

Send your site details to ACP →

Policy / monitoring tiers / urban habitats / delivery

Westminster BNG questions

These answers address local planning and habitat-delivery decisions. Use current official documents and site evidence when agreeing the project scope.

Is Westminster’s 30% biodiversity gain target mandatory?

The February 2026 Environment SPD encourages a 30% aspiration wherever possible. It does not impose a universal binding 30% minimum. Statutory BNG normally requires at least 10% for qualifying permissions, while exemptions and separate local ecology policies need their own checks.

Which City Plan applies while the new plan is being consulted on?

The City Plan adopted on 21 January 2026 replaced the 2021 version. The council’s New City Plan is a separate emerging review, with consultation responses invited before 11 December 2026. That process does not itself replace the adopted plan or introduce a binding new BNG percentage.

Does every Westminster application pay a monitoring contribution?

No. First establish statutory scope and the relevant long-term habitat obligations. The published contribution concerns council monitoring of qualifying significant on-site or off-site gains through the appropriate legal agreement. An exempt development does not automatically incur the charge.

Can a small site fall into the high monitoring band?

Yes. Any of the high-band criteria can trigger it, including creation of high- or very-high-distinctiveness habitat. Site area alone does not determine the band. Confirm the red-line area, number of monitored metric parcels and habitat types with the council.

Do green roofs automatically demonstrate statutory BNG?

No. Roof greening may contribute to the design, UGF and habitat proposals, but each calculation has different rules. Check substrate, planting, condition, delivery risk and management alongside structural and fire requirements. Then demonstrate the actual metric result where statutory BNG applies.

Does the report mean Westminster has never approved a Gain Plan?

No. The council recorded zero approved Gain Plans by its reporting cut-off of 31 December 2025. That historical finding does not establish the position in November 2026 or the current status of an individual application. Use the relevant planning register and condition record.

Can council greening projects provide units for my development?

A council project or nature-recovery opportunity is not automatically registered stock. Verify the gain-site reference, parcel, legal security, habitat match, remaining unallocated units and seller terms. Then record the allocation to the relevant development where off-site units are used.

Talk to ACP   /   Site enquiries

What does your site need next?

Tell us where the site is, what you plan to build and how far the application has progressed. We’ll use that context to discuss the surveys, calculations or plans your project needs.

What to have to handA red-line plan, an existing ecology report or a request from the council can help us scope the work. Start with whatever you already have.

Request a site-specific quotation

Start with the information you have. We ask for your email, site location and enquiry, with a telephone number at the final step.

STEP 1 OF 3

Where should we reply?

Start with your email. We will ask for your site location and project details next.

STEP 2 OF 3

Where is your site?

Add the address if you have it. These fields are optional.

STEP 3 OF 3

Tell us what you are planning

Share your proposal and the advice you need, then add your contact details.

We use your details to respond to your enquiry. Read our Privacy Policy.